LETTERS OF CONFIRMATION & CLARIFICATION

 

Confirming a Mutual Understanding

Further to our meeting of October 5, 20-, between the architect, Joe Stone & Son (Bentam) Ltd., and ourselves to discuss the statement of claim submitted by the contractor dated August, 20-, confirm the following:

a) The architect will grant an extension of nine weeks under clause 11 (6) and one week under clause 23(b) (this to be done under separate letter by the architect).

b) The sum for loss and expense has been agreed between the contractor and surveyor in the sum of ?5204.56. This sum has been agreed as the total loss and expense incurred by the contractor due to the delays described in the above claim and consequently items ?) and ?) b) in the notes on page 5 of the claim have been withdrawn; but excludes any costs in connection with Wordly Patent Glazing Ltd., or any nominated subcontractors, suppliers or statutory undertakings.

Would you please confirm receipt of this letter and that you are in agreement with its contents.


Key Expressions

Further to
the statement of claim
we confirm the following
grant
under separate letter
the sum for; for; sum; the sum of
has been agreed
incurred by
due to
have been withdrawn
exclude
in connection with
Would you
are in agreement with




 